Healthcare

Altru Replacement Hospital

Grand Forks, ND
Quick Facts/Highlights
  • 532,000 SF
  • 7 Floors
  • 200+ Patient Beds
  • 13,000+ Light Fixtures
  • Over $5M in Value Engineered Cost Savings
Service
Client
PCL/Community
Budget
$50,000,000
Markets
Healthcare
Project Overview

Working with longtime general contracting partner PCL, Gephart served as the electrical contractor for this state-of-the-art healthcare facility in Grand Forks, ND. The replacement hospital spans 532,000 SF, 7 floors, and has over 200 beds. Patients will benefit from a private NICU, private pre/post-operating rooms, and a dedicated trauma room.

Our Work

Gephart’s contributions included:

  • Installation of 13,000+ light fixtures
  • Installation of 13,000+ receptacles including 18 different types and colors
  • 8 power branches (normal A & B, critical A & B, equipment A & B, and life safety A & B)
  • 8 low-voltage systems (communications, fire alarm, access control, video surveillance, nurse call, infant security, paging speakers, clocks)
  • 15 KV tie into the existing campus emergency and distribution power plant
  • 3 MV transformers with busway connections into new electrical main switchgear
  • 3D layout and BIM coordination of all power distribution, low voltage cable trays, conduit racks, specialty imaging suites, and lighting
  • Field layout using Trimble Total Station
  • Large conduit bending offsite using Greenlee Bendworks
  • Use of prefab box assemblies during rough-in and plugtail devices during finishes
  • Use of offsite prefab facilities and personnel for stub-up conduits, fixture whips, fixture prep, and surface wireway construction
Success
  • Over $5M in cost savings through value engineering.
  • Strategic electrical equipment purchases reduced the overall schedule from 36 to 28 months.
  • Teamed with a local IBEW partner to fulfill crew needs of over 100 skilled electrical tradespeople, field oversight, offsite storage, and prefab warehouse space.
Quick Facts/Highlights
  • 532,000 SF
  • 7 Floors
  • 200+ Patient Beds
  • 13,000+ Light Fixtures
  • Over $5M in Value Engineered Cost Savings
Service
Client
PCL/Community
Budget
$50,000,000
Markets
Healthcare